List of implemented installations IM of metallurgical industry (sinter production)
#Address of implementationType of IM installationsApplication fieldYear of implementation (delivery)
1
Alchevs'k
Ukraine
Alchevsk iron and steel works
IM5-1.8-12
6 hoppers of sinter machines
(Sintering department)
2000
IM5-1.8-12
6 hoppers of charge
(Sintering department)
2004
IM5-1.8-12
6 hoppers of sinter machines
(Sintering department)
2014
2
Dunaújváros
Hungary
ISD Dunaferr
IM4-1.8-12
Hoppers №7, №8, №9
(Charge preparation shop)
2016
IM4-1.8-12
Hoppers №10, №11, №12
(Charge preparation shop)
2017
3
Yenakijeve
Ukraine
Yenakiieve iron and steel works
IM5-1.8-8
4 top hoppers of charge
(Sintering department)
2002
4
Zaporizhzhia
Ukraine
Zaporizhstal
IM3-0.8-14
Hoppers of dust collection of electric precipitator
(Sintering department)
2011
IM3-0.8-14
Hoppers of dust collection of electric precipitator
(Sintering department)
2011
IM3-1.1-10
8 hoppers and 2 prechambers of bag filter FRIR-6000 of gas cleaning installations of aspiration air of tail pieces of sinter machines №№ 1-3
(Sintering department)
2019
IM3-1.1-10
8 hoppers and 2 prechambers of bag filter FRIR-6000 of gas cleaning installations of aspiration air of tail pieces of sinter machines
(Sintering department)
2019
5
Kamianske
Ukraine
Dneprovsky Integratediron and steel works
IM5-1.8-12
6 hoppers of sinter machines
(Sintering department)
2003
IM5-1.8-12
6 hoppers of sinter machines
(Sintering department)
2003
IM5-1.8-12
6 hoppers of sinter machines
(Sintering department)
2004
IM5-1.8-12
6 hoppers of sinter machines
(Sintering department)
2004
IM5-1.8-6
8 hoppers charge compartment
(Sintering department)
2008
IM5-1.8-12
8 hoppers charge compartment
(Sintering department)
2008
6
Košice
Slovakia
U.S. Steel Kosice
IM4-1.6-14
Hopper of drum mixer
(Sintering plant)
2008
IM4-1.6-10
Charge hopper of sinter machine
(Sintering plant)
2008
IM3-1.2-9
9 hoppers of dust collection of electric precipitator
(Sintering plant)
2008
IM3-1.2-9
9 hoppers of dust collection of electric precipitator
(Sintering plant)
2008
IM4-1.6-10
Charge hopper of sinter machine
(Sintering plant)
2011
IM4-1.6-10
Charge hopper of sinter machine
(Sintering plant)
2011
IM4-1.6-14
Hopper of drum mixer
(Sintering plant)
2011
IM4-1.6-10
Charge hopper of sinter machine
(Sintering plant)
2011
7
Kryvyi Rih
Ukraine
ArcelorMittal Kryvyi Rih
IM5-1.8-16
4 refilling chutes of feeders of hammer crusherers
(Sintering department-3)
1997
IM5-0.6-6
6 production hoppers
(Sintering department-2)
1998
IM5-1.8-12
6 hoppers of sinter machines (bottom tier)
(Sintering department-2)
1998
IM5-1.8-12
6 hoppers of sinter machines (top tier)
(Sintering department-1)
2000
IM5-1.8-12
6 hoppers of sinter machines (bottom tier)
(Sintering department-1)
2000
IM3-0.8-6
6 production hoppers
(Sintering department-1)
2000
IM5-1.8-12
6 hoppers of sinter machines (top tier)
(Sintering department-2)
2000
IM5-1.8-12
6 charging chutes of sinter machines
(Sintering department-1)
2003
IM5-1.8-12
6 hoppers of limestone screening section
(Sintering department-3)
2003
IM5-1.8-12
6 charging chutes of sinter machines
(Sintering department-2)
2004
IM5-1.8-14
2 unloading chutes of conveyers, 6 loading and 6 unloading chutes of drums of secondary mixing.
(Sintering department-1)
2005
IM5-1.8-12
6 hoppers of sinter machines (bottom tier)
(Sintering department-2)
2009
IM5-1.8-16
2 hoppers of ore of dosage section
(Sintering department-3)
2009
IM5-1.8-12
6 hoppers of sinter machines (bottom tier)
(Sintering department-1)
2012
IM3-1.8-4
Hopper of dust collection of aspiration system of casting yard and bin trestle BF-6
(Blast-furnace plant-1)
2013
IM3-2.3-16
2 hoppers with limestone of charge hoppers block
(Sintering department-3)
2014
IM3-1.1-16
Dust hoppers of electric precipitator of sinter machine №6
(Sintering department-2)
2016
IM3-1.1-16
Dust hoppers of bag filter of sinter machine №5
(Sintering department-2)
2017
IM3-1.1-16
Dust hoppers of precipitator of sintering machine №4
(Sintering department-2)
2019
IM4-1.8-24
6 hoppers of sintering machines (top and bottom tiers)
(Sintering department-2)
2020
IM3-1.2-4
Collecting hopper of a section of dust unloading of bin trestle DP № 8
(Blast-furnace plant-1)
2021
8
Mariupol'
Ukraine
Ilyich iron and steel works
IM5-1.8-12
6 hoppers of sinter machines (bottom tier)
(Sintering plant)
1994
IM5-1.8-12
6 hoppers of sinter machines (bottom tier)
(Sintering plant)
1994
IM5-1.8-12
6 hoppers of sinter machines (top tier)
(Sintering plant)
1996
IM5-1.8-12
6 hoppers of sinter machines (top tier)
(Sintering plant)
1996
9
Mariupol'
Ukraine
Azovstal Iron and Steel Works
IM5-1.8-14
7 collecting hoppers
(Sintering plant)
1992
IM3-0.8-4
4 hoppers of a forming mixture
(Mechanized foundry)
1994
IM5-1.8-10
5 charge hoppers (bottom tier)
(Sintering plant)
1994
IM5-1.8-8
2 hoppers of 31-nd mark
(Sintering plant)
1994
IM3-0.8-2
Charging unit of a drum-mixer
(Sintering plant)
1995
IM5-0.4-1
Reloading unit of the conveyor
(Sintering plant)
1995
IM5-0.4-1
1 hopper of a section of stuffing flasks
(Mechanized foundry)
1995
IM5-1.8-10
5 charge hoppers ( top tier)
(Sintering plant)
1995
IM5-1.8-10
5 charge hoppers ( top tier)
(Sintering plant)
1995
IM3-1.0-2
2 production hoppers
(Sintering plant)
1997
IM3-1.0-2
2 production hoppers
(Sintering plant)
1997
IM5-1.8-2
2 hoppers of CLD BF №3
(Blast-furnace plant)
1997
IM5-1.8-2
2 hoppers of CLD BF №4
(Blast-furnace plant)
1999
IM5-0.8-5
4 hoppers of gathering of dust BF №6
(Blast-furnace plant)
2003
IM5-1.8-14
7 collecting hoppers
(Sintering plant)
2003
IM5-1.8-10
5 charge hoppers ( top tier)
(Sintering plant)
2003
IM5-1.8-10
5 charge hoppers ( top tier)
(Sintering plant)
2003
IM5-1.8-8
4 reception hoppers
(Sintering plant)
2003
IM3-0.8-2
Charging unit of a drum-mixer
(Sintering plant)
2008
IM3-1.8-8
4 silos of coal preparation shop
(Coke and chemical production)
2008
10
Temirtau
Kazakhstan
ArcelorMittal Temirtau
IM4-1.8-16
4 hoppers of sinter machine №6
(Sinter production)
2017
IM4-1.8-16
7 hoppers (№№201-206,208) of charge chain of sinter machine №5 of charge section
(Sinter production)
2018
IM4-1.8-16
7 hoppers (№№207,209-214) of charge chain of sinter machine №5 of charge department
(Sinter production)
2018
IM4-1.8-16
7 hoppers (№№215-221) of charge chain of sinter machine №5 of charge department.
(Sinter production)
2018
IM4-1.8-16
4 hoppers of sinter machine №5
(Sinter production)
2018
IM4-1.8-16
4 hoppers of sinter machine №7
(Sinter production)
2018
IM4-1.8-16
7 hoppers of charge chain of sinter machine №6 of charge section
(Sinter production)
2019
IM4-1.8-16
7 hoppers of charge chain of sinter machine №6 of charge section
(Sinter production)
2019
IM4-1.8-16
7 hoppers of charge chain of sinter machine №6 of charge section
(Sinter production)
2019
IM4-1.8-16
7 hoppers of charge chain of sinter machine №7 of charge section
(Sinter production)
2019
IM4-1.8-16
7 hoppers of charge chain of sinter machine №7 of charge section
(Sinter production)
2019
IM4-1.8-16
7 hoppers of charge chain of sinter machine №7 of charge section
(Sinter production)
2019
11
Ust'-Kamenogorsk
Kazakhstan
Ust-Kamenogorsk metallurgical complex
IM4-1.8-8
Hoppers of charge
(Charge curing workshop of lead plant)
2009
IM4-1.8-8
Hoppers of charge
(Charge curing workshop of lead plant)
2009
12
Cherepovets
Russia
Cherepovets iron and steel works
IM3-1.2-4
Hopper with dust of fired dolomite
2012
IM3-1.5-4
Hopper with dust of sintering production
(Aspiration installation Д-7а)
2013
IM3-1.5-4
Hopper with dust of sintering production
(Aspiration installation Д-7а)
2013
IM3-1.5-4
Hopper with dust of sintering production
(Aspiration installation Д-7а)
2013
IM3-1.5-4
Hopper with dust of sintering production
(Aspiration installation Д-7а)
2013